Requestcallback
Your name:*
Enter phone number:*
Дізнатись цін у
Your name:*
Enter phone number:*

Construction Dynamics for May 2020

28 may 2020 10:31
Construction Dynamics for May 2020

Dear customers! Your CITY HUB business class complex continues to grow. We prepared the dynamics of construction for May.

Reinforcing cages of the vertical elements of the basement of the 1st section were made.

The dismantling of the formwork from the grillage of the 1st section was carried out. As well as reinforcing the beam of the slab of the basement of the basement of the 2nd section.

Tower crane installed and working.

The construction site is being arranged.

A gas supply network has been laid.

More photos in the "Construction Progress" section.

Similar news

See news
18 April 2024 17:44
(Українська) ВІД ПОЧАТКУ 2024 РОКУ «ІНТЕРГАЛ-БУД» ВВІВ В ЕКСПЛУАТАЦІЮ 180 ТИС. КВ.М ЖИТЛА
(Українська) ВІД ПОЧАТКУ 2024 РОКУ «ІНТЕРГАЛ-БУД» ВВІВ В ЕКСПЛУАТАЦІЮ 180 ТИС. КВ.М ЖИТЛА

Sorry, this entry is only available in See news

(Українська) Гарантія добудови: «Інтергал-Буд» бере на себе воєнні ризики
(Українська) Гарантія добудови: «Інтергал-Буд» бере на себе воєнні ризики