Dynamics of construction in June

30 june 2020 13:17
Dynamics of construction in June

Dear customers! Your homes in CITY HUB business class are growing right before your eyes! And we are pleased to monthly record the dynamics and share information with you. Your attention is the dynamics of construction for June.

Installed slab basement "Section 2".

Vertical structures of the “Section 1” basement are installed.

Basement waterproofing work is nearing completion.

The installation of a pile field for parking has begun.