Dynamics of construction as of 30.09.20

01 october 2020 15:46
Dynamics of construction as of 30.09.20

Dear buyers! We bring to your attention the monthly fixation of the dynamics of the CITY HUB construction. Just look at how your business class complex, which is located in the central business district of Kyiv, is growing!

House №1

Section 1

Vertical structures of the 4 floor are installed.

The walls of the basement are being laid.

Section 2

Vertical structures of the 5 floor are installed.

The walls of the 1st floor are being laid.

The construction of a pile field for parking has begun.

The collector is being installed on the Kudryashova St.

Preparatory work is continues for the construction of the House №2.

More photos in the section "Construction progress"