Dynamics of construction as of 30.06.2021

01 july 2021 10:00
Dynamics of construction as of 30.06.2021

Dear buyers! We bring to your attention the monthly fixation of the dynamics of the CITY HUB construction. Just look at how your business class complex, which is located in the central business district of Kyiv, is growing!

House №1

Section 1

Vertical structures of the 18 floor are installed.

The walls of the 15 floort are being laid.

The device of ventilating channels, ladder marches proceeds - 67%.

Electrical work continues.

Section 2

Vertical structures of the 19 floor are installed.

The walls of the 15 st floor are being laid.

The device of ventilating channels, ladder marches proceeds - 70%.

Electrical work continues.

The construction of a pile field for parking has begun.

The collector is being installed on the Kudryashova St.

 

More photos in the section "Construction progress"