Dynamics of construction as of 28.02.2021

01 March 2021 16:08
Dynamics of construction as of 28.02.2021

Dear buyers! We bring to your attention the monthly fixation of the dynamics of the CITY HUB construction. Just look at how your business class complex, which is located in the central business district of Kyiv, is growing!

House №1

Section 1

Vertical structures of the 12 floor are installed.

The walls of the 5 floort are being laid.

The device of ventilating channels, ladder marches proceeds - 47%.

Electrical work has begun.

Section 2

Vertical structures of the 13 floor are installed.

The walls of the 8 st floor are being laid.

The device of ventilating channels, ladder marches proceeds - 54%.

Electrical work has begun.

The collector is being installed on the Kudryashova St.

Preparatory work is continues for the construction of the House №2.

More photos in the section "Construction progress"

Similar news

See news
18 April 2024 17:44
(Українська) ВІД ПОЧАТКУ 2024 РОКУ «ІНТЕРГАЛ-БУД» ВВІВ В ЕКСПЛУАТАЦІЮ 180 ТИС. КВ.М ЖИТЛА
(Українська) ВІД ПОЧАТКУ 2024 РОКУ «ІНТЕРГАЛ-БУД» ВВІВ В ЕКСПЛУАТАЦІЮ 180 ТИС. КВ.М ЖИТЛА

Sorry, this entry is only available in See news

(Українська) Гарантія добудови: «Інтергал-Буд» бере на себе воєнні ризики
(Українська) Гарантія добудови: «Інтергал-Буд» бере на себе воєнні ризики